DEM Wetland Application #02-0160
- Applicant name
- Organization name RIDEM Division of Planning & Development
- Location Lincoln
- Project information Blackstone River Bikeway, Segment 7A - Bike Path
Location description
Northern Terminus of Blackstone River Bikeway in Manville to Woonsocket Water Treatment Plant Access Drive, Lincoln, North Smithfield, Woonsocket, RI.
Historical information
-
June 02, 2009Permit Renewal Granted
-
June 02, 2009Application Review by Supervisor
-
June 01, 2009Application Review by Biologist
-
May 19, 2009Request to Renew Permit
-
March 13, 2009Permit Renewal Granted
-
March 13, 2009Application Review by Supervisor
-
March 09, 2009Application Review by Biologist
-
February 27, 2009Compliance Inspection
-
February 06, 2009Application Review by Supervisor
-
February 05, 2009Request to Renew Permit
-
January 25, 2008Permit Renewal Granted
-
January 24, 2008Application Review by Supervisor
-
August 23, 2007Compliance Inspection
-
June 04, 2007Application Review by Supervisor
-
May 30, 2007Request to Renew Permit
-
August 25, 2006Permit Renewal Granted
-
August 25, 2006Application Review by Supervisor
-
August 11, 2006Compliance Inspection
-
May 05, 2006Application Review by Supervisor
-
May 03, 2006Request to Renew Permit
-
July 25, 2005Permit Recorded in Land Evidence Record
-
May 24, 2005Alteration Permit Issued
-
May 20, 2005Supervisor Review of Alteration Project
-
February 02, 2005Engineering Evaluation
-
January 12, 2005Application to Revise Existing Submittal
-
December 22, 2004Application Review by Biologist
-
November 30, 2004Application Review by Supervisor
-
November 24, 2004Application to Revise Existing Submittal
-
November 04, 2004Application to Revise Existing Submittal
-
July 22, 2004Supervisor Review of Alteration Project
-
April 13, 2004Biologist Evaluation
-
March 26, 2004Public Notice Comment Review
-
February 24, 2004Comments Received
-
February 20, 2004Public Notice End Date
-
February 13, 2004Engineering Evaluation
-
January 06, 2004Public Notice Issued
-
December 31, 2003Public Notice Plan Review
-
December 31, 2003Application Review by Supervisor
-
December 19, 2003Plans Received for Public Notice
-
December 08, 2003Adequate for Public Notice
-
December 08, 2003Application Review by Supervisor
-
December 04, 2003Application Review by Biologist
-
October 03, 2003Applicant Response to Tech. Deficiency
-
September 15, 2003Technical Deficiency Letter Sent
-
September 12, 2003Application Review by Biologist
-
August 01, 2003Application Review by Engineer
-
July 24, 2003Applicant Response to Tech. Deficiency
-
May 15, 2003Technical Deficiency Letter Sent
-
May 15, 2003Application Review by Biologist
-
March 07, 2003Application Review by Engineer
-
February 19, 2003Applicant Response to Tech. Deficiency
-
November 04, 2002Technical Deficiency Letter Sent
-
October 30, 2002Application Review by Biologist
-
September 13, 2002Applicant Response to Tech. Deficiency
-
August 27, 2002Notified of Deficiency Via Phone Call
-
August 27, 2002Application Review by Biologist
-
August 06, 2002Application Review by Engineer
-
July 01, 2002Supervisor for Assignment
-
June 20, 2002Administrative Review
-
June 20, 2002Response to Administrative Deficiency
-
April 11, 2002Notified of Deficiency Via Phone Call
-
April 10, 2002Administrative Review
-
April 05, 2002Request to Alter Wetland Application
Need to Review a File? Email a Request for Records Form to DEM.FileReview@dem.ri.gov.
For wetlands questions, please visit dem.ri.gov/wetlands or email DEM.FWW@dem.ri.gov.Last updated 04-22-2025 05:43 PM